Client: Green Mountain Power

  • Estimated short-term and annual emissions of criteria pollutants for all possible generator ratings and three different operating load capacities 
  • Conducted Good Engineering Practice stack height analysis and identified generator exhaust stack locations, providing maximum dispersion of air pollutants
  • Developed a computer-based air pollution dispersion model to estimate ground-level air pollutant concentrations
  • Using the dispersion model, identified generator fuel use and exhaust stack parameters that would meet federal air quality requirements
  • Prepared air quality impact evaluation report for the state regulatory board